Barossa Rugby Precinct
- Address
- Menge Road, Tanunda (view map)
- Type
- The Big Project
- Status
- Current
- Anticipated completion date
- 22 December 2023
Project Budget: Total $4,729,908 ex GST, Grant $995,000, Council $3,424,908
Project Partners: Barossa Rams Rugby Club
The Barossa will soon see a new $4,729,908M ex GST Rugby Development built in Tanunda (next to the Rex), thanks to a $995,000 infrastructure grant from The Office of Recreation, Sport and Racing and a further $3,424,908 from The Barossa Council and the remainder put forward by the Barossa Rams.
The site will see the development of a new purpose-built, rugby facility to meet contemporary standards and provide high quality, inclusive, gender neutral and accessible infrastructure that will grow participation in rugby and encourage broad community use of multi-use facilities for associated activities such as Touch Football, extended primary school sporting activities. See architectural and Civil plans attached in the timeline below.
The Barossa Rams Rugby team will be relocated from Lyndoch Oval to the new purpose-built facility at Tanunda with, gender neutral, multi-use changerooms, clubroom, 1 x rugby pitch, 4 x LED lights providing 100 lux, carparking and internal roads.
The relocation of rugby is in response to pressure on infrastructure and scheduling at Lyndoch Oval, resulting from population growth in Southern Barossa and unprecedented growth and demand across all codes (rugby, football, netball, cricket, athletics). The new development will be fit-for-purpose infrastructure that meets the Australian standard for amateur rugby and associated touch football. This will contribute to player safety and improve player ability. The installation of lighting for night competition will allow participation growth in the sport, increase scheduling opportunities and broader the use of the site. The development will have inclusive infrastructure that is gender neutral, multi-use and at a standard that can host code finals.
Exterior Walls

September 2023
Windows and Services

August 2023
Veranda over Concourse

July 2023
Roof Complete and External Walls

July 2023
Lighting and Roof Work

July 2023
Framework is Complete

June 2023
Concrete Pad is complete

May 2023
Concrete Pour

May 2023
Pad for Clubrooms and Changerooms

April 2023
Sod Turning

February 2023
Contract Awarded

February 2023
Tender

December 2022
Planning

November 2022
Detailed Design

December 2021
Grant Awarded
June 2021
Concept Design

January 2021
Community Consultation

February 2017
Master Plan

November 2016
Seeking Community Feedback