Smyth Road, Tanunda - Bridge Remediation
- Address
- Smyth Road, Tanunda (view map)
- Type
- Bridge
- Status
- Completed
- Anticipated completion date
- 30 June 2022
The Smyth Road Bridge Remediation works will involve concrete repairs, minor drainage modifications, and the application of a product coating. Works are being carried out to extend the life of the bridge and to ensure that residents and visitors that access the bridge can do so safely.
These improvements are critical to providing safe river crossings for the road network, allowing the movement of goods and services.
Works are being completed and funded in conjunction with Light Regional Council.
Key works
- Concrete repairs
- Minor drainage modifications
- Product coating application
Cost
$115,000